Governor Ifeanyi Ugwuanyi’s led government of Enugu State is to spend a sum of N210 million naira in the refurbishment of toilet facilities at the international wing of the reconstructed Akanu Ibiam Airport (AIIA) Enugu, Southeast Nigeria.
This was disclosed to newsmen at a media briefing held during the weekend in Enugu by the Southeast Governor’s Forum (SEGF), Committee on the Airport Rehabilitation/Palliative Works, which said the present state of the toilets is embarrassing to the airport.
Some residents of the state who spoke under condition of anonymity on the said amount described it as “highly outrageous.”
It would be recalled that the reconstructed AIIA, was officially reopened by Nigeria’s Minister of Aviation, Senator Hadi Sirika last Sunday, after 370 days of its closure on the 24th of August 2019, to be precise.
Chairman of the Committee, Engr. Chris Okoye, who spoke on behalf of other members, presented a comprehensive and detailed situation report on the airport project which gulp the sum of N10billion naira released from the federal government as a special fund.
According to him, the amount to be spent on the proposed refurbishment of the modern toilet facilities though sounds outrageous, but what’s it, going by the quality of what will be fixed, adding that the facilities will be operated electronically.
Okoye recalled that the airport project commenced on November 4, 2019, with mobilization of equipment and personnel to the site, while Construction work began on November 17, 2019, after the installation of the necessary equipment on-site, hinting that the runway is 3km long, 45m wide with 7.5m shoulder on either side, also with an orientation of 08/26.
He reiterated that work on the airport runway has been 100 percent completed, contrary to speculation in some quarters that it is still work in progress, disclosing that one of the major facility in an international airport, the airfield lighting is 35 percent completed, while the runway shoulders have reached 85 percent completion.
Other areas the Chairman mentioned include the crash roads with five percent job done and no completion date stated; dredging/desilting of drainage on 70 percent completion.
The committee leader, equally hinted that the terminal building which work is expected to be completed on September 20, 2020; has reached 35 percent completion, while the entrance toll gate which commenced on July 20, 2020, was 75 percent completed.
Okoye, also put rate the drainage work at 72 percent, the aviation clinic at 52 percent, perimeter fence (50 percent), perimeter road (40 percent), sewage treatment plant (35 percent); water treatment plant (10 percent), administration block (10 percent) while nothing has been done about the fire watchtower as Okoye said they were waiting for inputs from the Nigerian Civil Aviation Authority (NCAA).
Most of the sections yet to be completed, according to him, comprised the second phase, which would not stop the operation of the airport.
On the issue of airfield lighting, Okoye stated that the following equipment will be installed from September 7: “Runway Centre Line Lights (4 weeks), Touch Down Zone Lights (4 weeks); CAT I Approach on RWY 08 – 4 weeks after the area is secured (Fence); CAT II Approach on RWY 26 – 6 weeks after the area is secured (Fence), Signage (November 2020) and Stop Bars (4 weeks)”.
He disclosed that once the above was completed, it will allow night operations at a visibility not less than 800 meters on RWY 08 and landings on RWY 26 at a RVR not less than 350 meters; that is assuming the Instrument Landing System is operational.
The Chairman said: “there are other projects being handled by NAMA in upgrading the navigational facilities, including installation of new satellite communication (VSAT), which facilitates the availability of RCAG (Remote Control Air to Ground), ATS/DS (Air traffic Services Direct Speech – Airport to Airport hotline communication via satellite), AFTN (Data exchanges between Akanu Ibiam and other airports around the world via satellite).
Post Disclaimer
The opinions, beliefs and viewpoints expressed by the author and forum participants on this website do not necessarily reflect the opinions, beliefs and viewpoints of Anaedo Online or official policies of the Anaedo Online.